Start Date - 10th April 2006
| |
The site is in Wickersley, Rotherham where our client is extending their two bedroom bungalow into three bedrooms with an en suite bathroom in the master. In addttion, a dining room will be added onto the kitchen to give the family a magnificent entertaining area.
| |
|
the extention will add about 80m2 of floor space to the existing house.
|
|
Pegged out and underway....
| |
we demolisted the small conservatory and brought in the 'boys toys' to excavate the footings.
| |
|
The soil was so good that we have had to dig down 1.5m to get a solid base.
| |
| |
|
24th April - Drains and soak aways in....
| |
| |
|
|
|
18m3 of concrete was pumped into the footings
| |
|
1st Stage roof on - July 06
| |
| |
| |
|
|
and the walls being prepared for rendering..
| |